Design

01
A site for the construction of a mini-hydroelectric power station on the Lodnari River (Georgia)

A site for the construction of a mini-hydroelectric power station on the Lodnari River (Georgia)

Land for construction of a mini-hydroelectric power station on the Lodnari River (Georgia). A land plot with confirmed hydrological characteristics and ready technical data for the construction of a hydroelectric power station is offered for sale. 📍 Location: Georgia, Lodnari River. Project type: turnkey construction of a mini-hydroelectric power station with the possibility of connecting to the grid and receiving a "green tariff". ⚙️ Main technical parameters: Indicator Value Upper level 460 m Lower level 298.8 m Total head 161.2 m Estimated water flow (Qdes) 2.0 m³/sec Turbine type Axial / Francis (calculated) Pressure pipeline material Steel, diameter 1.0–1.2 m Length of feeder channel 1.2 km Average annual generation 28.51 million kWh Installed capacity ≈ 4.0 MW Utilization factor 0.57 Price excluding VAT upon request Specific cost from $1.2 million/MW Project advantages: Professional team with international experience in HPP construction in Austria, Georgia, Kazakhstan and Kyrgyzstan. Full support: design, approvals, construction, installation, commissioning and financing. Support in obtaining permits and connecting to the Georgian power grid. Ready for implementation under the Build-Operate-Transfer model or joint investment. 🌍 Potential: Georgia is actively developing renewable energy and offers favorable conditions for investors: stable legislation, guaranteed electricity sales, and the possibility of exporting to Turkey and the EU.
Number of devices : 2
Total power (kW) 4
Static pressure (m) 161.2
Estimated flow rate (m3/s) 2
Impeller diameter (mm)
02
The Akavreta-Lodnari hydroelectric power station is located on a watercourse with a stable seasonal flow

The Akavreta-Lodnari hydroelectric power station is located on a watercourse with a stable seasonal flow

The Akavreta-Lodnari HPP is located on a watercourse with a stable seasonal flow rate and a favorable slope, ensuring high pressure utilization. Both units are housed in a single building, which reduces capital expenditures for construction, maintenance, and operation of the plant. The project includes: Installation of two Francis/Pelton turbines (depending on the specified pressure), a steel pressure pipeline with optimized pressure losses, modern generators, automation and telemetry systems. The expected average annual output is 69.4 million kWh, which ensures stable generation and predictable cash flow. Proposal formula (investment submission) We offer: Design Coordination Equipment supply (Europe / Turkey / Korea - according to the budget and investor requirements) Construction and installation Commissioning and commissioning Financing and co-investment, if necessary Turnkey implementation or partnership with an investor is possible.
Number of devices : 2
Total power (kW) 120013
Static pressure (m) 160
Estimated flow rate (m3/s) 1.78
Impeller diameter (mm)
03
The Gudauri hydroelectric power station is a high-pressure mountain station with a significant difference in elevation.

The Gudauri hydroelectric power station is a high-pressure mountain station with a significant difference in elevation.

The Gudauri HPP is a high-pressure mountain power plant with a significant elevation difference. The project involves the placement of two Francis turbines optimized for variable seasonal flow rates, with a pressure steel pipeline approximately 2.3 km long and 1.50 m in diameter. The plant is designed for long-term year-round operation and provides stable baseload generation, which can be sent to Georgia's grid, sold under contracts with industrial consumers, or exported to Turkey, which increases the project's marginality. Cooperation options: Sale of land plot and project implementation rights, Co-investment with share distribution, Full turnkey implementation: from feasibility studies and approvals to installation and commissioning, Possibility of attracting project financing through Georgian banks, funds, and private investors. Project advantages: High head guarantees high turbine efficiency and stable generation. Minimal environmental impact (no dam). Potential for increased capacity by optimizing flow rates and the pressure pipeline. Georgia maintains preferential treatment for renewable energy sources, market access, and export flexibility.
Number of devices 4
Total power (kW) 5.09 MW
Static pressure (m) 31
Estimated flow rate (m3/s) 6.1
Impeller diameter (mm) 1500
04
Akavreta hydroelectric power station is an object for implementation/joint investment

Akavreta hydroelectric power station is an object for implementation/joint investment

The Akavreta hydroelectric power plant is a high-pressure mountain hydroelectric power plant with a developed pressure tract and stable hydrology during peak flow periods. A separate water intake (3.05 + 3.05 m³/s) ensures balanced loading of both units and increased system energy efficiency. The plant is designed for two Francis hydroelectric units operating within an optimal range of operating pressures, ensuring high efficiency and low operating costs. The project is suitable for investment construction with subsequent sale of generation, for electricity export to Turkey, contracts with industrial consumers, and for green financing and ESG funds. What we provide: Design and adjustment of feasibility studies; Geodesy, hydrology, pressure calculations and turbine optimization; Obtaining permits and approvals; Equipment supply (EU/TR/CN — for investment profile); Installation and construction work; Commissioning and commissioning of hydroelectric power plants; Organization of financing or co-investment; Project advantages: Strong economic profile due to high pressure; Transparent revenue model over a 15–25-year horizon; Possibility of increasing output by optimizing hydraulics; Minimal impact on the riverbed and the environment
Number of devices : 2
Total power (kW) 25.02 MW
Static pressure (m) 253
Estimated flow rate (m3/s) 6.1
Impeller diameter (mm)
05
Combined model "Shrosha - Dzirula"

Combined model "Shrosha - Dzirula"

Combined model "Shrosha - Dzirula" Indicator Value Total capacity of the cascade ≈ 18.4 MW Total average annual generation ≈ 51-53 million kWh Generation type Spillway, channel, without a dam Optimization potential +8-12% of generation by adjusting the operating curves Advantages of the cascade: Small hydraulic footprint, fast approval times, high flow controllability, low cost per kWh. Implementation model for the investor We provide: Design and adjustment of the feasibility study Geology / surveying / hydraulic calculations Supply of turbines (EU / Turbine Pelton-Francis / China A-class) Construction work and installation Automation, SCADA, telemetry Commissioning and commissioning Possibility of co-investment or turnkey EPC Why the project is interesting High pressure + stable flow → low energy cost No dam → simple approvals Possibility of electricity export to Turkey The project is suitable for green loans and ESG instruments Quick implementation model 18–28 months
Number of devices
Total power (kW)
Static pressure (m)
Estimated flow rate (m3/s)
Impeller diameter (mm)
06
Mini-hydropower plants in Kyrgyzstan. Construction sites and modernization of existing hydropower plants

Mini-hydropower plants in Kyrgyzstan. Construction sites and modernization of existing hydropower plants

We offer a full range of services for the implementation of hydropower projects in Kyrgyzstan. Our team supports the project at every stage: from site selection and preliminary hydrological calculations to equipment delivery, construction, and commissioning of the plant. What we do: Selection and sale of sites for the construction of mini-hydropower plants (rivers, pressure heads, existing structures). Preliminary assessment of profitability and technical solutions. Design (feasibility studies, working documentation, 3D models of the water supply system and turbine hall). Project coordination with government agencies, energy companies, and environmental organizations. Equipment supply (Francis, Pelton, Kaplan, Pelton turbines, generators, control systems). Installation, commissioning, and commissioning. Organizing financing and supporting banking programs. Modernization of Soviet-era hydropower plants: turbine replacement, reconstruction of water pipelines, efficiency and output improvement. We offer turnkey services, including legal and engineering support. For investors, we offer transparent project economics, including calculations of IRR, payback periods, and tariff scenarios. Why Kyrgyzstan? High fluctuations and stable water flows. Favorable terms for electricity exports. Government programs supporting renewable energy sources. Development of local energy infrastructure. If you need a reliable partner capable of not only selling a plot but also actually building a working hydroelectric power plant, contact us.
Number of devices 4
Total power (kW) 4-50,000
Static pressure (m) 60.7- 300
Estimated flow rate (m3/s) 2
Impeller diameter (mm) 1755
07
Sale of land and construction of mini-hydroelectric power plants in Kazakhstan

Sale of land and construction of mini-hydroelectric power plants in Kazakhstan

We offer comprehensive solutions for the construction of hydroelectric power plants in Kazakhstan, from site selection to turnkey project implementation. 📍 What we offer: Selection and evaluation of sites suitable for mini-hydroelectric power plant construction. Development of design documentation taking into account hydrology and topography. Full coordination with government agencies and obtaining permits. Supply and installation of equipment, including turbines, generators, and pipelines. Commissioning and connection to the power grid. 💼 Benefits of working with us: Experience in the construction and modernization of hydroelectric power plants in Kazakhstan and other CIS countries. Financing available at 8% per annum in tenge through Kazakhstani banks. Integrated approach: design, construction, approvals, commissioning, and operational support. Customized solutions for investors and industrial clients. 🌍 Investment potential: Kazakhstan is actively developing renewable energy and offers stable conditions for investors: guaranteed electricity sales and the ability to scale projects.
Number of devices 4
Total power (kW) 21.174
Static pressure (m) 161.2
Estimated flow rate (m3/s) 43.5
Impeller diameter (mm) 1320
08
Project cascade mini-hydroelectric power station on the river Arym

Project cascade mini-hydroelectric power station on the river Arym

Project objective: to construct a cascade of mini-hydroelectric power plants on the Arym River to generate clean electricity and sell it at a "green tariff." 🌊 1. General concept: The Arym River has a natural elevation difference, making it ideal for a cascade of mini-hydroelectric power plants. The hydrological regime is snow-glacial: the maximum flow rate is up to 7 m³/s during the melting period, and the minimum is about 1.3 m³/s in winter. A single pressure penstock with a diameter of 1400 mm and a flow velocity of approximately 3 m/s is used, providing an average annual operating flow rate of 4.62 m³/s. ⚙️ 2. Cascade structure: The cascade consists of four stages, each with its own pressure head and diversion length. The effective total head of the cascade is ≈1065 m, with total losses of only 38.9 m. No. Name Effective head, m Capacity, MW 1 Arym-1 ≈254 ≈11.0 2 Arym-2 ≈224 ≈9.6 3 Arym-3 ≈195 ≈8.4 4 Arym-4 ≈392 ≈11.7 Total: ≈40.7 MW ⚡ 3. Energy potential The total installed capacity of the cascade is about 40.7 MW. Turbine equipment has an efficiency of up to 85%, which guarantees high efficiency and stable generation. 💰 4. Investment attractiveness The project belongs to the category of highly profitable renewable energy facilities. At a tariff of 4.42 soms/kWh, the expected annual revenue provides a payback period of 4.5 to 6 years. Advantages: minimal construction risks; simple installation of a single 1400 mm diameter string; reduced capital expenditures on metal structures and supports; scalability (a second string for increased capacity). 🏗️ 5. Conclusion: The cascade option on the Arym River is a technically feasible and economically feasible project, ensuring stable power generation, a rapid return on investment, and long-term operational reliability. The project is ready for further design, approval, and investment.
Number of devices : 8
Total power (kW) 40 MW
Static pressure (m) 1065
Estimated flow rate (m3/s) 3
Impeller diameter (mm) 1400
09
An inactive mini-hydroelectric power plant in the Almaty region is for sale.

An inactive mini-hydroelectric power plant in the Almaty region is for sale.

Location: Almaty region, Kazakhstan Plant capacity: 800 kW Land area: 93 hectares (owned) Property description: An inactive mini hydroelectric power plant located in a picturesque area of the Almaty region is offered for sale. The plant was built and operated for a limited time - about 4 months. Work was suspended due to design errors and the need for reconstruction of the dam. Current status: Land plot - owned, 93 hectares. Hydraulic structures - require inspection and reconstruction. Electromechanical equipment is partially preserved. There is a possibility of restarting after adjustments to the design. Potential: The property is of interest to investors wishing to restore or modernize existing infrastructure with minimal time to obtain permits. Thanks to the existing site and water management structures, the project can be adapted for a new mini hydroelectric power plant with a capacity of up to 1 MW or a complex with energy storage. Terms of sale: Price and transaction details - upon request. Sale of both the property and the land plot is possible, as well as the transfer of the project for joint development.
Number of devices : 2
Total power (kW) 800
Static pressure (m) 7
Estimated flow rate (m3/s) 3
Impeller diameter (mm) 480
10
Hydroelectric power station for sale in Zukhzidi, Georgia.

Hydroelectric power station for sale in Zukhzidi, Georgia.

We offer for sale three ready-to-use mini-hydropower plants with a total installed capacity of 1.96 MW to 5 MW, as well as land plots for construction and expansion to 5 MW. All facilities are technically ready and economically attractive to investors. Hydropower Plant 1 - 1.96 MW (operating) Average annual output: 8.54 GWh Number of units: 1 Status: In operation since 2023 Total project cost: USD 5,800,000 Projected payback: Thanks to a stable tariff and reliable equipment, the project provides a sustainable income. HPP 2 — 3.3 MW (under development) Average annual output: 9.04 GWh Number of units: 2 Construction status: in progress (planned completion — 2026) Investment value of the site and equipment: USD 4,400,000 Potential for increasing capacity with additional modules and upgrading the installed equipment. HPP 3 — 5 MW project (at the design stage) Estimated average annual output: 21 GWh Projected status: development stage Possibility of scaling and integration into grid solutions Attractive site with high hydrological efficiency, ready for construction Technical and economic justification at the final stage Investment advantages: Finished facilities with confirmed parameters Possibility of increasing capacity and scaling projects Support at all stages of the transaction: from the purchase of a ready-made asset to arranging financing High profitability against the background of current tariffs for the purchase of electricity Environmental and social effect — use of renewable energy
Number of devices : 1
Total power (kW) 2 MW / 3 MW / 5 MW
Static pressure (m) 1065
Estimated flow rate (m3/s) 7.9
Impeller diameter (mm) 1755
11
Batu Hampar Hydroelectric Power Station, Indonesia, 2011

Batu Hampar Hydroelectric Power Station, Indonesia, 2011

In 2011, Gugler Water Turbines GmbH successfully completed a project to equip the Batu Hampar hydroelectric power station in Indonesia with modern Austrian-made turbines. This innovative solution enabled the efficient use of existing hydroelectric facilities without extensive construction, ensuring stable renewable energy generation.
Number of devices : 1
Total power (kW) 970 kW
Static head (m) 62.6 m
Estimated flow rate (m3/s) 1.8 m³/s
Impeller diameter (mm) 507 mm
12
Cartiera del Maglio Hydroelectric Power Plant – EPF, Italy, 2011

Cartiera del Maglio Hydroelectric Power Plant – EPF, Italy, 2011

In 2011, Gugler Water Turbines GmbH equipped the Cartiera del Maglio hydroelectric power station in Italy with a modern Austrian-made turbine. This project, located at a historic site (a former paper mill), demonstrates the feasibility of modernizing older hydroelectric power plants with minimal construction work, ensuring efficient green energy generation.
Number of devices : 1
Total power (kW) 610 kW
Static pressure (m) 5.8 m
Estimated flow rate (m3/s) 12.0 m³/s
Impeller diameter (mm) 1600 mm
13
Nuevo Imperial Hydroelectric Power Station, Peru, 2011

Nuevo Imperial Hydroelectric Power Station, Peru, 2011

In 2011, Gugler Water Turbines GmbH successfully completed a project to equip the Nuevo Imperial hydroelectric power station in Peru with a powerful Austrian-made turbine. This solution enabled the efficient use of the region's hydroelectric potential without large-scale construction, ensuring stable generation of renewable energy from existing facilities.
Number of devices : 1
Total power (kW) 4,110 kW
Static head (m) 61.5 m
Estimated flow rate (m3/s) 7.5 m³/s
Impeller diameter (mm) 1023 mm
14
El Sindigo Project, Panama, 2011

El Sindigo Project, Panama, 2011

In 2011, the company successfully completed the El Sindigo project in Panama—a high-pressure hydropower facility where modern turbines and pumping units were installed to efficiently convert water flow energy. This project underscores the company's expertise in designing and supplying equipment for the challenging conditions of Central America, taking into account the region's topography and hydrological characteristics.
Number of devices : 3
Total power (kW) 18,000 kW
Static head (m) 240.0 m
Estimated flow rate (m3/s) 2.8 m³/s
Impeller diameter (mm) 1050 mm
08
Sale of land in Georgia, Kyrgyzstan, Kazakhstan, and Armenia for the construction of a hydroelectric power station

Sale of land in Georgia, Kyrgyzstan, Kazakhstan, and Armenia for the construction of a hydroelectric power station

💧 Akavreta Hydroelectric Power Plant Project, Georgia. A promising site for the construction of the Akavreta small hydroelectric power plant, located on the Akavreta River in an energy-rich region of Georgia, is available for sale. The project boasts stable hydrological characteristics and high investment attractiveness. ⚙️ Main parameters: River: Akavreta Upper level: 460 m Lower level: 417.5 m Total head: 42.5 m Water flow: 2.0 m³/s Head loss (λ): 0.015 Pipeline: steel, Ø 1.2–1.0 m Length of tailrace: 40.9 m Turbine type: Kaplan / Francis (specified based on design results) Average annual output: ~8–10 million kWh Cost of electricity: 5–6 c/kWh 🌍 Project advantages: Stable water regime and reliable hydrology Support for renewable energy development at the state level Possibility of obtaining a “green tariff” Potential for electricity export to Turkey and the EU Low environmental impact and compact infrastructure 📈 Akavreta HPP — a ready-made site for investments in clean and profitable energy in Georgia. The project combines optimal technical and economic indicators with long-term generation sustainability. 📞 Contact
Number of devices 4
Total power (kW) 40000
Static pressure (m) 460
Estimated flow rate (m3/s) 43.5
Impeller diameter (mm)

Turbine pumps

Automated control system

Turnkey equipment

Service

Modernization

01

Development of a feasibility study for a hydroelectric power station

02

We are designing a technical solution

03

Development of financing schemes

04

Coordination of design documentation

05

Construction and commissioning

100+ years of experience
in design

We implement projects
in difficult conditions

Task analysis and consultation

Development of a technical solution

Project approval and finalization

Implementation or transfer of the project

How long will it take for the project to pay off and what is the projected income?

Key factors:

  1. Location and Geography. Construction in the Caucasus or Central Asia, in mountainous areas or under challenging climatic conditions, can increase construction time and costs.
  2. Average annual electricity production. The more stable the water flow and the higher the production, the more reliable the income, but production is affected by seasonality and the hydrological conditions of the site.
  3. The nature of the site. The size, topography, accessibility of infrastructure, and grid connectivity all impact construction timelines and costs.
  4. Electricity tariffs and sales models. Electricity can be sold directly to the government under a "green tariff" or to private consumers, such as mining farms. Each scheme has its own profits and risks.
  5. Financing. Interest rates, loan currency, and investment structure directly impact ROI. For example, in Kazakhstan, lending at 8% in tenge is considered very profitable.

Estimated payback periods:

  • Mini hydroelectric power plants (1–10 MW): 5–8 years.
  • Medium-capacity hydroelectric power plants (10–50 MW): 6–12 years, depending on tariffs, financing, generation and other factors.

What technical, financial and natural risks may affect the implementation of hydroelectric power plants?

How reliable are the station, turbines, and equipment, and are there any guarantees of safe operation?

Have all permits been obtained and are there any possible delays due to bureaucracy or legislation?

How will the investor be able to control the construction, costs, and compliance with the project deadlines?

English

× Close